Hanjin Heavy Industries and Construction Co., Ltd. v. Ibañez

Kinds of Employment — Project Employment: The Written Contract and the Termination Reports
Subject Home
16px
←Previous: ALU-TUCP v. National Labor Relations CommissionPrevious case
Primary source ↗Next: Cocomangas Hotel Beach Resort v. ViscaNext case→

On this page

  • Gist
  • Facts
  • Issue
  • Ruling
  • Ratio
  • Doctrine
  • Provisions
Primary source ↗

Title

Hanjin Heavy Industries and Construction Co., Ltd. v. Ibañez

Case Decision Date

G.R. No. 170181 June 26, 2008

Hanjin, a construction company, dismissed a tireman, a crane operator, welders and a warehouseman on April 15, 2002, claiming they were project employees on the LRT/MRT Line 2 project, which was winding down. The workers said Hanjin had drawn them from a work pool for years — North Harbor, Manila International Port, Batangas Port, La Mesa Dam. Hanjin first claimed written three-month project contracts, then admitted on appeal that none were executed. It relied instead on a single DOLE termination report, payroll entries for a "completion bonus," and quitclaims. The Supreme Court (Third Division, Chico-Nazario, J.) held the workers regular. A written contract is not indispensable, but its absence "has been construed by this Court as a red flag," because it is the evidence that the employee was informed of the project's "duration and scope" at hiring. A lone termination report filed only at the end of the last project, after years on others, "is not only unconvincing, but even suspicious." The "completion bonus" was an afterthought, and the quitclaims were not for valuable consideration.

Core Doctrine

"[E]ven though the absence of a written contract does not by itself grant regular status to respondents, such a contract is evidence that respondents were informed of the duration and scope of their work and their status as project employees," and its absence "has been construed by this Court as a red flag." "Absent any other proof that the project employees were informed of their status as such, it will be presumed that they are regular employees." "The failure of an employer to file a Termination Report with the DOLE every time a project or a phase thereof is completed indicates that respondents were not project employees."

Case Digest (G.R. No. 170181)

Case DigestWeeks 10–11 - The Employer-Employee Relationship and the Kinds of Employment

Hanjin Heavy Industries and Construction Co., Ltd. v. Ibañez

G.R. No. 170181 · June 26, 2008 · Third Division

Kinds of Employment — Project Employment: The Written Contract and the Termination Reports

Petitioner: Hanjin Heavy Industries and Construction Co., Ltd., Hak Kon Kim and/or Jhunie AdajarRespondent: Felicito Ibañez, Aligwas Carolino, Elmer Gacula, Enrique Dagotdot and Ruel Calda
Gist

Hanjin, a construction company, dismissed a tireman, a crane operator, welders and a warehouseman on April 15, 2002, claiming they were project employees on the LRT/MRT Line 2 project, which was winding down. The workers said Hanjin had drawn them from a work pool for years — North Harbor, Manila International Port, Batangas Port, La Mesa Dam. Hanjin first claimed written three-month project contracts, then admitted on appeal that none were executed. It relied instead on a single DOLE termination report, payroll entries for a "completion bonus," and quitclaims. The Supreme Court (Third Division, Chico-Nazario, J.) held the workers regular. A written contract is not indispensable, but its absence "has been construed by this Court as a red flag," because it is the evidence that the employee was informed of the project's "duration and scope" at hiring. A lone termination report filed only at the end of the last project, after years on others, "is not only unconvincing, but even suspicious." The "completion bonus" was an afterthought, and the quitclaims were not for valuable consideration.

Core Doctrine

"[E]ven though the absence of a written contract does not by itself grant regular status to respondents, such a contract is evidence that respondents were informed of the duration and scope of their work and their status as project employees," and its absence "has been construed by this Court as a red flag." "Absent any other proof that the project employees were informed of their status as such, it will be presumed that they are regular employees." "The failure of an employer to file a Termination Report with the DOLE every time a project or a phase thereof is completed indicates that respondents were not project employees."

Note: The decision cites the Labor Code by its pre-2015 numbers; under DOLE Department Advisory No. 01, s. 2015, Article 280§ is now Article 295. Nine workers sued; five are respondents here, though the Labor Arbiter's award, reinstated by the CA and affirmed, lists all nine. The decision dates both the complaint and the termination report April 11, 2002 — four days before the dismissal it gives as April 15. The fallo identifies the CA case as CA-G.R. SP No. 87474. The NLRC had found no proof that the workers were employed before 1997, when MRT construction began. The Supreme Court instead faulted Hanjin for failing to rebut their account of earlier projects with records in its own custody.

Facts

  • Hanjin Heavy Industries and Construction Co., Ltd., a foreign construction company, employed Felicito Ibañez (tireman, from 2000), Elmer Gacula (crane operator, from 1992), Enrique Dagotdot and Aligwas Carolino (welders, from 1995 and 1994) and Ruel Calda (warehouseman at the main office, from 1996).
  • The workers said they were members of a work pool dispatched to Hanjin's projects — North Harbor (1992–94), Manila International Port (1994–96), Batangas Port (1996–98), the Batangas Pier and La Mesa Dam — and that when Hanjin dismissed them on April 15, 2002 it still had MRT II and III in progress and hired replacements. Their unrebutted service across many projects is what made Hanjin's single termination report suspicious.
  • Hanjin first alleged written contracts hiring them as project employees for three months, automatically renewed and ending with the LRT/MRT Line 2 Package 2 and 3 project, but never produced them; on appeal it admitted that "due to a lapse in management procedure, no such employment contracts were executed." The missing contract is the "red flag" at the centre of the case.
  • Hanjin relied on a termination report filed with DOLE on April 11, 2002, payroll pages for April 4–20, 2002 marked "completion bonus" (fifteen days' wages each), and quitclaims the workers signed. (The workers denied receiving any completion bonus.)
  • The Labor Arbiter (April 30, 2003) held them regular and illegally dismissed. The NLRC (May 7, 2004) reversed. The CA (July 28, 2005) reinstated the Labor Arbiter's backwages, separation pay and litigation expenses, but deleted the damages.

Issue

Were the construction workers project employees whose employment ended with the LRT/MRT project, or regular employees illegally dismissed?

Ruling

Regular employees, illegally dismissed; the CA affirmed. "Due to petitioners' failure to adduce any evidence showing that petitioners were project employees who had been informed of the duration and scope of their employment, they were unable to discharge the burden of proof." They were also dismissed without notice and hearing.
"IN VIEW OF THE FOREGOING, the instant Petition is DENIED. This Court AFFIRMS the assailed Decision of the Court of Appeals in CA-G.R. SP No. 87474, promulgated on 28 July 2005, declaring that the respondents are regular employees who have been illegally dismissed by Hanjin Heavy Industries & Construction Company, Limited, and are, therefore, entitled to full backwages, separation pay, and litigation expenses. Costs against the petitioners."

Ratio

  • The test. A specific project whose duration and scope were specified at engagement (Art. 280§). Rehiring of construction workers project to project does not by itself make them regular, but only if they knew the terms each time.
  • Knowing consent. Project-to-project contracts are valid if agreed to "knowingly and voluntarily" (Caramol; Salinas); employees must be informed (Abesco).
  • The red flag. The absence of a written contract does not by itself make an employee regular, but the contract is the evidence of notice; without other proof, regular status is presumed (D.O. 19-93, Sec. 3.3(a)§).
  • One termination report. Reports must be filed for each completed project or phase; a lone report after years of continuous work on other projects is "suspicious."
  • No completion-bonus undertaking. The "bonus" was an afterthought, not tied to completion or service (D.O. 19-93, Secs. 2.2(f), 3.4§).
  • Quitclaims. Not for valuable consideration, so they do not bar claims to what regular employees are owed.
  • Due process. No notice and hearing.

Doctrine

  • The employer must prove that project employees were informed, at hiring, of the duration and scope of their project (Art. 280§, now Art. 295).
  • The absence of a written project contract is a "red flag"; without other proof, the workers are presumed regular (D.O. 19-93§).
  • Failure to file a termination report after each completed project indicates the workers are not project employees.
  • A "completion bonus" is an indicator only if the employer undertook to pay it; an afterthought payment proves nothing.
  • Quitclaims without reasonable consideration do not bar claims.
Limits. The Court did not hold a written contract indispensable. It held that, with no contract and no other proof of notice, the employer cannot discharge its burden. The work-pool arrangement is treated as a device for avoiding regularization, not condemned in itself.

Full Digest — Recitation Format

Gist

The relationship of this case to the requested topic, Kinds of Employment — Project Employment: The Written Contract and the Termination Reports, is DIRECT.
A construction company called its long-serving workers project employees of one rail project, but could produce no project contracts, only one termination report, a dubious "completion bonus" and quitclaims. The Supreme Court (Third Division, Chico-Nazario, J.) held them regular and illegally dismissed. The central doctrine is that project status must be proved by showing the workers were told the project's duration and scope at hiring; the missing written contract and missing termination reports are red flags against the employer.

Facts

  • 1992 – 2000: The respondents are hired (Gacula 1992, Carolino 1994, Dagotdot 1995, Calda 1996, Ibañez 2000).
  • 1992 – 1998 and after: Assignments, per the workers, to North Harbor, Manila International Port, Batangas Port, Batangas Pier and La Mesa Dam.
  • April 4–20, 2002: The payroll marked "completion bonus."
  • April 11, 2002: The termination report to DOLE; nine workers file for illegal dismissal.
  • April 15, 2002: Hanjin dismisses them.
  • April 30, 2003: The Labor Arbiter finds illegal dismissal.
  • May 7, 2004: The NLRC reverses.
  • July 28, 2005: The CA reinstates the Labor Arbiter, minus damages.
  • June 26, 2008: The Supreme Court affirms the CA.

Arguments of the Parties

A. Petitioners (Hanjin and its officers)
The workers were project employees for the LRT/MRT Line 2 project, informed of company rules posted at campsites, laid off with notice when the project wound down; Hanjin complied with indicators (e) and (f) of D.O. No. 19§ — a termination report and a completion bonus; the workers signed quitclaims; and the absence of written contracts does not make them regular.
B. Respondents (the workers)
Their work was necessary to Hanjin's business; they were a work pool drawn on for many projects over years; they signed no project contracts; and Hanjin continued other projects and replaced them.
C. Common Ground
Their work for Hanjin, the April 15, 2002 dismissal, the April 11, 2002 termination report, and the absence of written contracts.

Issue

A. Main Issue (Topic/Subtopic-Centered)

Whether the workers were project employees or regular employees.

B. Secondary Issues

  1. What weight the termination report, the "completion bonus" and the quitclaims carry.
  2. Whether the dismissals observed due process.

Ruling

  • Main issue: regular. "For these reasons, respondents are to be considered regular employees of HANJIN."
  • Secondary issue 1: little. The lone report is "not only unconvincing, but even suspicious"; the bonus "cannot be used to determine whether or not the employment was regular or merely for a project"; the quitclaims "cannot prevent them from seeking claims to which they are entitled."
  • Secondary issue 2: no. "Respondents were not served notices informing them of the particular acts for which their dismissal was sought."
Dispositive portion (verbatim):
IN VIEW OF THE FOREGOING, the instant Petition is DENIED. This Court AFFIRMS the assailed Decision of the Court of Appeals in CA-G.R. SP No. 87474, promulgated on 28 July 2005, declaring that the respondents are regular employees who have been illegally dismissed by Hanjin Heavy Industries & Construction Company, Limited, and are, therefore, entitled to full backwages, separation pay, and litigation expenses. Costs against the petitioners.
SO ORDERED.

Ratio

  1. The test. "[T]he principal test for determining whether particular employees are properly characterized as 'project employees'... is whether or not the project employees were assigned to carry out a 'specific project or undertaking,' the duration and scope of which were specified at the time the employees were engaged" (Art. 280§).
  2. Rehiring in construction. "[T]he length of service or the re-hiring of construction workers on a project-to-project basis does not confer upon them regular employment status," but "[s]hould the terms of their employment fail to comply with this standard, they cannot be considered project employees."
  3. Notice. Under Abesco, the duration and work are "defined in an employment agreement and... made clear to the employees at the time of hiring."
  4. Red flag. "While the absence of a written contract does not automatically confer regular status, it has been construed by this Court as a red flag."
  5. Presumption. "Absent any other proof that the project employees were informed of their status as such, it will be presumed that they are regular employees in accordance with Clause 3.3(a)" (D.O. 19-93§).
  6. Termination reports. "The failure of an employer to file a Termination Report with the DOLE every time a project or a phase thereof is completed indicates that respondents were not project employees."
  7. Completion bonus. "A completion bonus, if paid as a mere afterthought, cannot be used to determine whether or not the employment was regular or merely for a project."
  8. Quitclaims. They "do not appear to have been made for valuable consideration."
  9. Doubt. "[I]f doubts exist between the evidence presented by the employer and that by the employee, the scales of justice must be tilted in favor of the latter."

Doctrine

Doctrines / Rules / Principles Laid Down

  1. Project status requires proof the workers were informed of the project's duration and scope at hiring (Art. 280§, now Art. 295).
  2. No written contract and no other proof: presumed regular (D.O. 19-93, Sec. 3.3(a)§).
  3. A termination report is required for each completed project or phase.
  4. A completion bonus counts only if undertaken in advance.

Distinctions / Limitations / Qualifications

  • Contrast ALU-TUCP v. NLRC: there the workers were confined to identified expansion projects with durations fixed at hiring.
  • The construction-industry rule that rehiring does not by itself make workers regular survives, but the employer must prove the project terms for each engagement.

Topic/Subtopic Integration (Mandatory)

Classification: DIRECT. ALU-TUCP defines a project; Hanjin says how an employer proves one. The paper trail — a contract telling the worker the project and its expected end, and a termination report to DOLE when each project ends — is the employer's burden. A work pool drawn on for years and cut off with one report at the end looks like regular employment, and the law treats it so.

Separate Opinions

None. Chico-Nazario, J. wrote the Decision; Ynares-Santiago (Chairperson), Austria-Martinez, Nachura and Reyes, JJ. concurred.

Cited Laws & Provisions

Every statute, rule, and issuance the decision turns on — the text as written, and the work it does in this case.

Labor Code

Article 280, Labor Code

Regular and casual employment

Labor Code (P.D. No. 442, as amended), Book VI (Post Employment), Title I (Termination of Employment)

The provisions of written agreement to the contrary notwithstanding and regardless of the oral agreement of the parties, an employment shall be deemed to be regular where the employee has been engaged to perform activities which are usually necessary or desirable in the usual business or trade of the employer, except where the employment has been fixed for a specific project or undertaking the completion or termination of which has been determined at the time of the engagement of the employee or where the work or service to be performed is seasonal in nature and the employment is for the duration of the season.

An employment shall be deemed to be casual if it is not covered by the preceding paragraph: Provided, That any employee who has rendered at least one year of service, whether such service is continuous or broken, shall be considered a regular employee with respect to the activity in which he is employed and his employment shall continue while such activity exists.

Renumbered as Article 295 by DOLE Department Advisory No. 1, series of 2015; decisions before that cite it as Article 280.

Why it is cited here

The exception Hanjin had to prove. Project employment is employment "fixed for a specific project or undertaking the completion or termination of which has been determined at the time of the engagement." The principal test is assignment to a specific project "the duration and scope of which were specified at the time the employees were engaged." Construction workers rehired project to project may remain project employees, but only if they were told the scope and duration of each project at hiring. Hanjin had no evidence that they were.

DOLE Issuance

DOLE Department Order No. 19, s. 1993 (Guidelines Governing the Employment of Workers in the Construction Industry)

Indicators of project employment; when project employees become regular; completion bonus

Sections 2.2, 3.3(a) and 3.4 — as quoted in this decision

2.2 Indicators of project employment. - Either one or more of the following circumstances, among others, may be considered as indicators that an employee is a project employee. (a) The duration of the specific/identified undertaking for which the worker is engaged is reasonably determinable. (b) Such duration, as well as the specific work/service to be performed, is defined in an employment agreement and is made clear to the employee at the time of hiring. (c) The work/service performed by the employee is in connection with the particular project/undertaking for which he is engaged. (d) The employee, while not employed and awaiting engagement, is free to offer his services to any other employer. (e) The termination of his employment in the particular project/undertaking is reported to the Department of Labor and Employment (DOLE) Regional Office having jurisdiction over the workplace within 30 days following the date of his separation from work, using the prescribed form on employees' terminations/dismissals/suspensions. (f) An undertaking in the employment contract by the employer to pay completion bonus to the project employee as practiced by most construction companies.

3.3(a) Project employees whose aggregate period of continuous employment in a construction company is at least one year shall be considered regular employees, in the absence of a "day certain" agreed upon by the parties for the termination of their relationship. Project employees who have become regular shall be entitled to separation pay.

3.4 ... An undertaking by the employer to pay a completion bonus shall be an indicator that an employee is a project employee. Where there is no such undertaking, the employee may be considered a non-project employee. The pro-rata completion bonus may be based on the industry practice which is at least the employee's one-half (1/2) month salary for every 12 months of service ...

Excerpted as the decision quotes it; the "day certain" paragraph of 3.3(a) and the remainder of 3.4 are omitted here.

Why it is cited here

The guidelines Hanjin invoked and failed. It pointed to indicators (e) and (f): a termination report and a completion bonus. But only one termination report was filed, at the end of the last project, though the workers had served on others. Hanjin showed no undertaking to pay a completion bonus. The payroll "bonus" was a flat fifteen days' wages for April 4–20, 2002, unrelated to completion or to years of service, while 3.4 sets at least half a month per twelve months. Without proof the workers were told of their project status, Section 3.3(a) presumes them regular.

Study digest — refer to the full text of the decision for accuracy. https://lawphil.net/judjuris/juri2008/jun2008/gr_170181_2008.html

Cited laws & provisions

Article 280, Labor Code

Labor Code

Regular and casual employment

Labor Code (P.D. No. 442, as amended), Book VI (Post Employment), Title I (Termination of Employment)

The provisions of written agreement to the contrary notwithstanding and regardless of the oral agreement of the parties, an employment shall be deemed to be regular where the employee has been engaged to perform activities which are usually necessary or desirable in the usual business or trade of the employer, except where the employment has been fixed for a specific project or undertaking the completion or termination of which has been determined at the time of the engagement of the employee or where the work or service to be performed is seasonal in nature and the employment is for the duration of the season.

An employment shall be deemed to be casual if it is not covered by the preceding paragraph: Provided, That any employee who has rendered at least one year of service, whether such service is continuous or broken, shall be considered a regular employee with respect to the activity in which he is employed and his employment shall continue while such activity exists.

Renumbered as Article 295 by DOLE Department Advisory No. 1, series of 2015; decisions before that cite it as Article 280.

Why it is cited here

The exception Hanjin had to prove. Project employment is employment "fixed for a specific project or undertaking the completion or termination of which has been determined at the time of the engagement." The principal test is assignment to a specific project "the duration and scope of which were specified at the time the employees were engaged." Construction workers rehired project to project may remain project employees, but only if they were told the scope and duration of each project at hiring. Hanjin had no evidence that they were.

Full entry below ↓

DOLE Department Order No. 19, s. 1993 (Guidelines Governing the Employment of Workers in the Construction Industry)

DOLE Issuance

Indicators of project employment; when project employees become regular; completion bonus

Sections 2.2, 3.3(a) and 3.4 — as quoted in this decision

2.2 Indicators of project employment. - Either one or more of the following circumstances, among others, may be considered as indicators that an employee is a project employee. (a) The duration of the specific/identified undertaking for which the worker is engaged is reasonably determinable. (b) Such duration, as well as the specific work/service to be performed, is defined in an employment agreement and is made clear to the employee at the time of hiring. (c) The work/service performed by the employee is in connection with the particular project/undertaking for which he is engaged. (d) The employee, while not employed and awaiting engagement, is free to offer his services to any other employer. (e) The termination of his employment in the particular project/undertaking is reported to the Department of Labor and Employment (DOLE) Regional Office having jurisdiction over the workplace within 30 days following the date of his separation from work, using the prescribed form on employees' terminations/dismissals/suspensions. (f) An undertaking in the employment contract by the employer to pay completion bonus to the project employee as practiced by most construction companies.

3.3(a) Project employees whose aggregate period of continuous employment in a construction company is at least one year shall be considered regular employees, in the absence of a "day certain" agreed upon by the parties for the termination of their relationship. Project employees who have become regular shall be entitled to separation pay.

3.4 ... An undertaking by the employer to pay a completion bonus shall be an indicator that an employee is a project employee. Where there is no such undertaking, the employee may be considered a non-project employee. The pro-rata completion bonus may be based on the industry practice which is at least the employee's one-half (1/2) month salary for every 12 months of service ...

Excerpted as the decision quotes it; the "day certain" paragraph of 3.3(a) and the remainder of 3.4 are omitted here.

Why it is cited here

The guidelines Hanjin invoked and failed. It pointed to indicators (e) and (f): a termination report and a completion bonus. But only one termination report was filed, at the end of the last project, though the workers had served on others. Hanjin showed no undertaking to pay a completion bonus. The payroll "bonus" was a flat fifteen days' wages for April 4–20, 2002, unrelated to completion or to years of service, while 3.4 sets at least half a month per twelve months. Without proof the workers were told of their project status, Section 3.3(a) presumes them regular.

Full entry below ↓